February 29, 2024: Stairs

Image
  Time to replace the temporary stairs. The metal framework from the front landing to the main floor. There's a main span and footers welded on to support the individual wooden steps. Bolted to the heavy wooden beams. It's the same going up to the second floor. Nelson is using the new support to reach the beam for final sanding.

February 24, 2024: Shelves and Heaters

Image
  Catching up, we find the boilers and the hot water tank are installed. One boiler is for the driveway snowmelt; the other is for the radiant heat and hot water. On the main floor, Tanner has built the shelves in the play area. As well as in the kitchen.

February 7, 2024: Room by Room

Image
 Upstairs, Luis and Jaime continue to install the paneling in the ceilings. Office. In the mechanical room, Peak is putting in the ductwork and air handlers.

February 4, 2024: It's A Beautiful Day

Image
  No "White Bird," but it's pretty nice out.

February 1, 2024: New Month; New Update

Image
  The new month begins but it is just about the end of the sunshine, with a storm scheduled to roll in tomorrow. The ductwork for the kitchen hood is in. Bobby has the tilework complete in one of the bathrooms. More to go. Jaime and Luis are installing the paneling in the master bedroom.